GOVERNMENT OF INDIA
MINISTRY OF NEW AND RENEWABLE ENERGY
RAJYA SABHA
UNSTARRED QUESTION NO-1353
ANSWERED ON-26.03.2012
(a) whether Government has fixed any target for generation of solar power under the Jawaharlal Nehru National Solar Mission (JNNSM) during the last three years;
(b) if so, the details thereof;
(c) the achievements made during the last three years, State-wise;
(d) whether the targets have been achieved; and
(e) if not, the reasons therefor?
ANSWER
THE MINISTER OF NEW AND RENEWABLE ENERGY(DR. FAROOQ ABDULLAH)
(a): No, Sir. Targets have been fixed for First Phase of JNNSM (2010-13).
(b): Details are attached as Annexure ‘A’.
(c): The State-wise achievements made during the Phase-I of Mission are attached as Annexure ‘B’.
(d): The targets of Phase-I of JNNSM are to be met by 2013.
(e) Does not arise.
Twitter Link To This Post
Facebook Link To This Post
Google + Link To This Post
YS Chowdary Facebook
YS Chowdary Twitter
YS Chowdary Blog
YS Chowdary Wikipedia
No comments:
Post a Comment